Dubai Land Department project register, as of Nov 2026.
Dubai Land Department lists 6 finished projects by LMD, and 4 under construction.
Finished projects
6
Units in finished projects
1,203
Villas in finished projects
1,138
Finished after the completion date DLD holds now
2 of 6
Median gap for those finished after it
25 months
Under construction
4
DLD replaces a project's completion date when the project is given more time, and keeps no earlier dates. So we compare each finish date with the date DLD holds now, not with the first date it registered.
We have recorded the completion dates of their 3 projects under way since Jun 12, 2026. None has moved since then.
We log changes to DLD completion dates only since Nov 2026, so a date that moved before then doesn't show as a move.
We list 2 off-plan projects by LMD, in Dubai Maritime City and Wasl Gate.
Which project by LMD is due next?
The Pier Residence, due in Jun 2027. The last of their projects on sale is due in Mar 2028.
Does LMD usually finish on time?
Dubai Land Department lists 6 finished projects by LMD. Of the 6 with both dates on its register, 4 were finished by the completion date it holds now and 2 after it. DLD replaces that date when a project is given more time and keeps no earlier dates, so this doesn't show how far a date moved before. Each project's page shows its own register entry.
How much does LMD ask for up front?
It varies, but all 2 of their plans ask for more than 10% to book. Each project page shows its own plan.