Dubai Land Department project register, as of Nov 2026.
Dubai Land Department lists 6 finished projects by Refine, and 3 under construction.
Finished projects
6
Units in finished projects
799
Villas in finished projects
54
Finished after the completion date DLD holds now
1 of 6
Median gap for those finished after it
14 months
Under construction
3
DLD replaces a project's completion date when the project is given more time, and keeps no earlier dates. So we compare each finish date with the date DLD holds now, not with the first date it registered.
Since Jun 12, 2026, DLD has moved the completion date of 1 of their 4 projects under way, by 6 months on average.
We log changes to DLD completion dates only since Nov 2026, so a date that moved before then doesn't show as a move.