118 off-plan projects by Emaar Properties in 18 areas of Dubai, with their prices, payment plans and handover dates.
Address Residences The Bay, Dubai Harbour
118off-plan projects for sale
18areas of Dubai
AED 850Kthe lowest starting price
About Emaar Properties
Emaar Properties is a Dubai developer founded in 1997 by Mohamed Alabbar. Its shares have traded on the Dubai Financial Market since 2000. In May 2026 Dubai Holding became its largest shareholder, with 29.73 per cent, after it bought the 22.27 per cent stake held by the Investment Corporation of Dubai.
Its home building in the UAE is done by Emaar Development. Emaar sold 20 per cent of that unit on the same market in November 2017. By November 2026 it owned just over 79 per cent and offered to buy the remaining shares. In 2026 it said the group had delivered more than 130,900 homes in Dubai and its other markets since 2002.
Its older communities include Emirates Living (Emirates Hills, The Springs, The Meadows and The Lakes), Dubai Marina, built around a 3.5 km man-made marina, and Arabian Ranches. It built Downtown Dubai, with The Dubai Mall and Burj Khalifa, which opened on 4 January 2010. Its newer master plans include Dubai Hills Estate, developed jointly with Meraas, Dubai Creek Harbour, Emaar Beachfront and Emaar South, a 50-50 venture with Dubai South.
In February 2009, as Dubai property prices fell, it put new projects and launches on hold and kept building the ones already under way. In March 2009 about 200 buyers asked it to cancel or postpone three projects launched in 2008: Warsan Estate, Asmaran and Maysan. It said it would consider the request.
Booking is cheap with them: 109 of 113 plans ask for 10% or less up front.
They tend to price below the resale market: 61 of the 77 projects we checked start below the usual price per square foot of similar homes sold through Dubai Land Department, typically by about 10%.
They don't stick to one part of town: their projects are spread over 18 areas, with no more than 21 in any one of them.
Their record
Dubai Land Department project register, as of Nov 2026.
Dubai Land Department lists 193 finished projects by Emaar Properties, and 117 under construction.
Finished projects
193
Units in finished projects
47,976
Villas in finished projects
16,984
Finished after the completion date DLD holds now
12 of 188
Median gap for those finished after it
2.5 months
Under construction
117
These counts include the project companies registered behind Emaar Properties, as developers in Dubai often set up one per project.
DLD replaces a project's completion date when the project is given more time, and keeps no earlier dates. So we compare each finish date with the date DLD holds now, not with the first date it registered.
5 finished projects have no completion date or no finish date on the register, so they are left out of that count.
We have recorded the completion dates of their 122 projects under way since Jun 12, 2026. None has moved since then.
We log changes to DLD completion dates only since Nov 2026, so a date that moved before then doesn't show as a move.
Prices and payment plans
What they cost
Apartments start from AED 850K, villas and townhouses from AED 1.6M.
Their most expensive project, Lavita at The Oasis, starts from AED 38M, far above the AED 2M at which half their projects start.
How you pay
The plan you'll see most often from them is 10 / 70 / 20, in 71 of 113 projects: booking first, then construction, then handover.
How many projects does Emaar Properties have on sale?
We list 118 off-plan projects by Emaar Properties, spread over 18 areas. Dubai Creek Harbour, Dubai Hills Estate, and Emaar South have the most.
Are projects by Emaar Properties priced above the market?
Usually not. Of the 77 we compared with Dubai Land Department sales of similar homes, 61 start below the usual price per square foot and 13 above.
Which project by Emaar Properties is due next?
Address Residences The Bay, due in Dec 2026. The last of their projects on sale is due in Jun 2031.
Does Emaar Properties usually finish on time?
Dubai Land Department lists 193 finished projects by Emaar Properties. Of the 188 with both dates on its register, 176 were finished by the completion date it holds now and 12 after it. DLD replaces that date when a project is given more time and keeps no earlier dates, so this doesn't show how far a date moved before. Each project's page shows its own register entry.
How much does Emaar Properties ask for up front?
10% in their most common plan, 10 / 70 / 20. 109 of their 113 plans ask for 10% or less to book.